Leetherm were awarded the contract as main contractor and PSCS to carry out remedial works to 5 timber frame local authority houses in Kill, Co. Waterford. The works included the installation of party wall fire barriers and fire stopping, installation of cavity wall ties, ventilation upgrades to the timber structure & painting. All houses were occupied throughout the duration of the works.
Ceol na Mara – Waterford Council Project Kill
Client
Waterford City & County Council
Project Dates
July 2017 to October 2017
Project Value
€102,000.00
Design Team
Architects – Dermot Bannon Architects
Quantity Surveyors – O Brien Quantity Surveyors